QuestionQ159
Risk Management and Security FrameworksA project team member has just identified a new project risk. The risk event is assessed as having a significant impact but a low probability on the project. If it occurs, it will delay the project by three weeks, which will create a new project risk. What should the project manager do with this risk event?
- A Add the identified risk to the issues log.
- B Add the identified risk to a quality control management control chart.
- C Add the identified risk to the low-level risk watchlist.
- D Add the identified risk to the risk register.