QuestionQ138

Managing Projects

You are the project manager for a large project that will extend across several time zones. You will use project team members from several departments. Project team members will not work on the project full-time and will join and leave the project according to assignments in the project schedule.

Which project management plan can you create to help manage when project team members will be brought onto and released from the project team?

  • A Staffing management plan
  • B Team management plan
  • C Project management plan
  • D Human resources management plan
Explanation

A staffing management plan establishes how project personnel will be acquired, assigned, made available, and released throughout the project. It is the plan that aligns part-time, cross-departmental team participation with the project schedule and resource availability.