QuestionQ126

Managing Projects

Which of the following activities result in change requests?

Each correct answer represents a complete solution. Choose all that apply.

Choose three
  • A Preventive actions
  • B Inspection
  • C Defect repair
  • D Corrective actions
Explanation

Project change requests may recommend corrective action to realign performance, preventive action to reduce the likelihood of future problems, or defect repair to correct a nonconforming deliverable. Inspection is a verification technique, rather than a change-request activity.