Which project-management risk event would be used if you changed the activity sequence to reduce the probability that the project will be delayed?

Explanation

Risk avoidance changes the project plan or approach to eliminate a threat or minimize its probability. Resequencing activities to make a delay less likely is therefore an avoidance response. Enhancing and exploiting are strategies for positive risks (opportunities).