You are serving as a project manager in your organization. You are approaching the final stages of project execution and preparing for the final risk-monitoring and controlling activities. For the project archives, which of the following is an output of risk monitoring and control?

Explanation

Risk monitoring and control can identify a need for corrective or preventive action; those needs are issued as requested changes. Risk audits are performed as part of the monitoring activity, and qualitative and quantitative risk analysis are separate analysis processes.