QuestionQ29

VerifiedManaging and Mitigating Cyber Risk

You are the project manager for a new project in your organization. You and the project team have identified the project risks, completed risk analysis, and are planning the most suitable risk responses. Which of the following tools is most effective for selecting the most appropriate risk response?

Explanation

Decision tree analysis evaluates alternative risk-response actions by mapping possible outcomes and, where applicable, comparing their probabilities and expected values. This supports selection of the response with the most favorable anticipated result.