QuestionQ26

VerifiedManaging and Mitigating Cyber Risk

You are a project manager for the TYU project and are planning risk mitigation. You need to identify the risks that require more in-depth analysis. Which of the following activities will help you do this?

Explanation

Qualitative risk analysis assesses identified risks according to their probability and impact and prioritizes them. This prioritization identifies the risks that warrant more detailed analysis, such as quantitative risk analysis.

Community Discussion

No comments yet. Be the first to start the discussion!