QuestionQ161

Managing and Mitigating Cyber Risk

Your project team wants to perform qualitative analysis on risks that have been identified and documented in Project Web Access for the project. You want to create a table that records the likelihood and affect of each risk on the project. What type of chart or table should be created for the project risks?

  • A Risk Breakdown Structure
  • B Risk Probability and Impact Matrix
  • C Risk Review Table
  • D Risk Impact and Affect Matrix
Explanation

A risk probability and impact matrix is used for qualitative risk analysis to assess risks according to their likelihood and their impact on the project.