QuestionQ26

VerifiedDisaster Recovery Planning Process

Which of the following teams is responsible for implementing and executing the disaster recovery plan, including its test plans?

Explanation

The Technology Team is responsible for implementing the technical recovery procedures and carrying out disaster-recovery testing. Planning responsibilities focus on developing and maintaining the plan; support responsibilities provide assistance rather than executing the technical recovery work.