QuestionQ121

VerifiedRisk Assessment

Which of the following terms denotes evaluating the potential interruptions to a department’s operations resulting from failure of its internal systems?

Explanation

A business impact analysis evaluates the operational consequences of interruptions, including information-system failures. When the analysis is limited to one department or team, it is a team-wide BIA rather than an analysis spanning a branch, country, or the entire organization.

Learn more

Community Discussion