QuestionQ117

VerifiedBusiness Impact Analysis and Business Continuity Plan

XYZ Inc. is a distinguished organization that provides a range of internet services and solutions. The organization is developing an Internet-based messaging application that is currently in the analysis phase. According to the analysis, if a disaster destroyed the primary server, the secondary server could handle the traffic load for only four hours because it has limited memory and storage capabilities. Therefore, the primary server would have to be restored and operational within four hours. Which technical term best defines this four-hour period?

Explanation

A Recovery Time Objective (RTO) specifies the target maximum time within which a system or service must be restored after a disruption. Here, the primary server must be operational within four hours before the secondary server can no longer sustain the required traffic load.