QuestionQ53

VerifiedNAS, PowerScale, and OneFS

A company has an existing 8-node F800 Isilon cluster with two Dell Z9100 Ethernet back-end switches, running OneFS 8.2.0. The company plans to add 72 A200 nodes to the cluster. What is the minimum number of additional switches needed to support this configuration?

Explanation

An 80-node A200/F800 cluster on OneFS 8.2 requires a redundant leaf-spine back-end topology. Each of the A and B networks requires two leaf switches and one spine switch. Retaining the two existing Z9100 switches as one leaf per network leaves one leaf switch and one spine switch to add on each side, for four additional switches.

Learn more