QuestionQ25

VxRail Post-Deployment procedures

An administrator has deployed a VxRail dynamic node cluster with a VxRail-managed vCenter.

Which task must be completed?

Explanation

When VxRail deploys its own internally managed vCenter Server appliance rather than joining an existing customer-managed vCenter, that vCenter instance starts in a time-limited evaluation licensing state, so a required post-deployment task is to assign a valid vCenter Server license to it; storage policy configuration and manual VAMI-based vCenter version updates are optional administrative tasks, not mandatory post-deployment requirements tied to the VxRail-managed vCenter model.

Community Discussion

No comments yet. Be the first to start the discussion!