QuestionQ9

VerifiedPowerMax Upgrades and Migrations

A Storage Architect is responding to a Request for Proposal (RFP). The customer currently runs its SAP HANA database and applications on a two-site Hitachi enterprise platform. Dell proposes a technology refresh using a PowerMax 8500 system, which requires migrating data from the existing Hitachi arrays to the new PowerMax V4 arrays.

To validate the current configuration for migration through the “My Work” portal, which two components, besides hosts and SAN switches, can the Architect verify?

Choose two
Explanation

Migration configuration validation covers the end-to-end infrastructure participating in the move: the source storage arrays, target PowerMax arrays, hosts, and SAN switches. Hitachi storage is the source array environment, and the PowerMax 8500 array is the migration target; application-license and virtual-machine CPU settings are outside this storage migration validation scope.