VerifiedDell Midrange Storage Solutions Planning, Sizing and Design

A technical architect is assisting a customer in preparing for a data-center maintenance window. All applications must fail over to the disaster-recovery site, and the customer also wants to test its disaster-recovery plan.

Which PowerStore Manager replication option should be used to meet the customer’s need, and from which site should it be run?

Explanation

A planned failover is used for planned downtime and disaster-recovery testing because it synchronizes the destination with the source before production moves, avoiding data loss. The operation is initiated from the source site; the destination DR site then becomes the production site.