Before failing back to the production infrastructure following a DR exercise, what must be done to preserve the audit history generated during the DR event?

Explanation

Audit history created while the Disaster Recovery Instance is active must be synchronized back to the Production Instance before failback. Replicating the changes from DR to production preserves a complete audit trail and prevents DR-period records from being lost.