QuestionQ61

VerifiedSecurity Program Management and Oversight

During the annual review of the system design, an engineer identified several issues with the currently released design. According to best practices, which of the following should be performed next?

Explanation

A released design is a controlled configuration baseline. Changes to it require a change control process to record and evaluate the requested change, obtain the required approval before implementation, incorporate approved changes, release the updated item, and track the request to closure.

Learn more