QuestionQ82
Business ContinuityFive minutes after a power outage occurred at a data center, a CO2 system was triggered automatically. What caused the CO2 system to activate?
- A High temperatures activated the fire suppression system.
- B RPO settings were configured to be applied in a short time frame.
- C A cooling system set off the CO2 system in order to protect the equipment.
- D RTO settings were configured to be applied in a short time frame.