A partner is migrating a client from on premises to a hybrid cloud. Based on the following project-status information, the initial project timeline estimates must be revised:

Question Image

Which of the following documents must be revised to best reflect the project's current status?

Explanation

A work breakdown structure (WBS) organizes the project into defined work components and supports project planning and control. When the estimated durations of discovery, design, implementation, and knowledge transfer change, the WBS should be updated to reflect the revised work-phase estimates. A business impact analysis concerns continuity impacts, an SLA defines service levels, and an SOW defines contractual work requirements rather than the detailed current project-work breakdown.