QuestionQ35

VerifiedSection 3: Implement Backups and Disaster Recovery

A Citrix Engineer must return an environment to normal operations after a Disaster Recovery (DR) event.

Which two tasks does Citrix recommend for moving users from the backup datacenter to the primary datacenter?

Choose two
Explanation

Citrix failback restores the primary access path while preventing new user connections from continuing to use the disaster-recovery access path. Enabling access to the primary datacenter and blocking access to the Disaster Recovery datacenter directs subsequent user access to the restored production site.

Learn more

Community Discussion