QuestionQ20

AI Infrastructure Operations and Troubleshooting

A data center experienced a power outage, and the UCS X-Series servers did not automatically restart when power was restored. The configuration must be changed so these servers are prioritized to boot as quickly as possible and resume their work. Which set of power-policy configurations meets these requirements?

Explanation

For UCS X-Series servers, Always On as the Power Restore state causes the server to power on after power is restored. High Power Priority gives the server preferential initial power allocation, and enabled Power Profiling allows the power manager to determine the server’s power needs. The default Processor Package Power Limit is sufficient because no requirement calls for increasing CPU package power consumption.