QuestionQ90

Governance, Risk, and Responsible Use

You are a project manager evaluating stakeholder messages that teammates have drafted regarding Claude’s role in a workflow. Which two messages are appropriate for stakeholder communication about Claude?

Each correct answer represents part of the solution.

Choose two
Explanation

Claude can generate factually incorrect or contextually inconsistent output, and mitigation techniques do not eliminate that risk; critical information still requires validation. Appropriate stakeholder communication therefore states the integration’s limitations and known failure modes, while honestly defining Claude’s assistance role and the decisions that remain with humans.